Demolishing an unlisted building in a conservation area usually needs planning permission, and doing it without is an offence. Section 196D read clause by clause, with the size limits and the prior approval steps.
In a conservation area, demolishing an unlisted building usually needs planning permission, and doing it without that permission is a criminal offence under section 196D of the Town and Country Planning Act 1990. Small buildings and low walls are the main exceptions, and some still need the council's prior approval.
New to this? Start with Grade I, Grade II* and Grade II: Does the Grade Change What You Can Do?
Our post on what an Article 4 direction takes away from a house in a conservation area dealt with altering a house. Taking a building down sits under a different rule, and this post reads that rule clause by clause.
Why does knocking a building down count as development?
Section 55 of the 1990 Act defines development, and its subsection (1A) says building operations include "demolition of buildings". So, as a starting point, pulling a building down is development like any other building operation.
Subsection (2)(g) then lets the Secretary of State take some descriptions of building out of that definition by direction. Planning Practice Guidance explains that, under the direction now in force, demolishing a building of no more than 50 cubic metres in volume is not development at all.
What does section 196D say, subsection by subsection?
The section has nine subsections. Read in order, they create the offence, define it, allow one defence and fix the penalty:
- Subsection (1), the offence: it is an offence to carry out, or cause or permit to be carried out, "relevant demolition without the required planning permission".
- Subsection (2), conditions: it is also an offence to break any condition or limitation attached to a planning permission for relevant demolition.
- Subsection (3), the definition: relevant demolition means demolishing a building in a conservation area in England, other than the kinds of building that section 75 of the Planning (Listed Buildings and Conservation Areas) Act 1990 takes out of the regime.
- Subsection (4), the defence: four matters, set out further down, all of which the accused person has to prove.
- Subsections (5) to (7), penalties: on summary conviction, imprisonment up to the general limit in a magistrates' court, a fine, or both; on indictment, up to two years' imprisonment, a fine, or both. Subsections (6) and (7) only adjust this for older offences.
- Subsection (8), the size of a fine: the court must have particular regard to any financial benefit the person has gained, or seems likely to gain, from the offence.
- Subsection (9), permission after the event: a grant of planning permission after the offence does not affect liability for it.
Which buildings fall outside "relevant demolition"?
Section 75(1) of the Listed Buildings Act names four kinds of building that its section 74 does not apply to, and section 196D borrows that list:
- Listed buildings, which have their own consent regime.
- Ecclesiastical buildings for the time being in use for ecclesiastical purposes; section 75(5) adds that a minister's residence is not treated as one.
- Scheduled monuments, meaning buildings included in the schedule kept under the Ancient Monuments and Archaeological Areas Act 1979.
- Buildings described in a direction made by the Secretary of State under section 75(2).
That last item matters most to owners of ordinary houses and gardens. According to Planning Practice Guidance, the direction made in 2015 covers any building under 115 cubic metres, and gates, fences and walls below set heights.
Where does the guidance draw the lines?
Paragraph 064 of the guidance sets out the position for a building in a conservation area that is not listed. Measure the volume before anything else:
- 50 cubic metres or less: not development, so no planning permission is needed.
- Under 115 cubic metres: permitted development under Part 11 of Schedule 2 to the General Permitted Development Order 2015, subject to that Part's conditions, which can include prior approval.
- Gates, fences and walls: also permitted development under Part 11 if less than 1 metre high where they abut a highway, public footpath, bridleway, waterway or open space, or less than 2 metres high anywhere else.
- Anything else: an application for planning permission to the council.
Where demolition is part of a redevelopment, the guidance says its details can go into the planning application for the new scheme. The council can then consider the demolition alongside the rest, and may attach conditions to it.
When is a small demolition still not permitted?
Class B of Part 11 grants the permitted development right, then withholds it in certain cases. The one owners meet most is paragraph B.1(a): the right does not apply where someone with an interest in the land let the building become unsafe or uninhabitable, and repair or temporary support could still make it safe.
Paragraph B.1(b) also withholds the right for anything that is relevant demolition. That is why the 115 cubic metre line matters so much: above it, the Part 11 route is closed.
How does prior approval work for the smaller cases?
Unless the demolition is urgent, or is "excluded demolition" such as work on land that already has planning permission for redevelopment, Class B sets these steps before work starts:
- Apply to the council for a determination of whether its prior approval is needed for the method of demolition and any restoration of the site.
- Describe the work in writing, with a statement that the site notice is up, and pay any fee.
- Display a site notice on or near the land for at least 21 days within the 28 days from the date the council received the application.
- Wait for one of three outcomes: written word that prior approval is not needed; the approval itself, where the council said within 28 days that it is needed; or 28 days passing with no determination.
- Carry out the work as approved, or as described if approval was not needed, within five years.
The guidance calls prior approval "a light-touch process" that applies where the principle of the development is already established. It is about how the building comes down and how the site is left, not whether it may go.
Is there a defence when a building has to come down in an emergency?
Section 196D(4) gives one defence, and it is narrow. The person accused must prove every one of these:
- Urgency: the demolition was urgently necessary in the interests of safety or health.
- No practical alternative: safety or health could not practicably be secured by repair, or by temporary support or shelter.
- Minimum measure: the demolition went no further than was necessary.
- Written notice: the council was told in writing as soon as reasonably practicable.
Part 11 carries the same idea for the smaller cases. Where demolition is urgently necessary for safety or health, the developer must give the council a written justification as soon as reasonably practicable.
In either case, dated photographs and a short engineer's note made at the time are the best evidence an owner can keep.
Can permission granted later put things right?
Permission granted afterwards does not undo the offence. Subsection (9) is explicit that a later grant of planning permission for the work leaves the person's liability as it was.
A council may still be willing to regularise what is on the ground, but that is a planning decision, not an amnesty. The criminal question is settled by what happened on the day of the demolition.
"Permission granted afterwards does not undo the offence."
Are you sure the outbuilding is unlisted?
Before relying on any of this, check that the building is not listed in its own right, or protected as part of a listed building's curtilage. Our post on outbuildings and garden walls in the grounds of a listed building explains how that can happen.
If it is listed, section 196D does not apply. The guidance says no planning permission or prior approval is needed to demolish a listed building, but listed building consent may be.
Measuring volume sounds simple until a lean-to shares a wall with the house, or a garage has a pit beneath it. That is where an architect earns their place: settling what counts as the building, and putting the figures in writing before anyone asks.
If the demolition is one part of a larger plan for the site, HeritageAI's Preliminary Planning and Heritage Appraisal (PPHA) is a sensible first step. Its AI writes the appraisal automatically from the details you give and emails it to you; it is a first read for planning, not professional advice, as the Old Posingford sample shows.
Plenty of old garages, stores and sheds in conservation areas are worth more repaired than replaced. Owners who measure, ask and record before they act are keeping the small buildings that give a street its grain.
If there is a building on your plot you are thinking of taking down, Book a 30-minute call with Giles and we will look at a first read on it together.